"Working group" studies the state of investment projects in the Shurtan oil and gas production department
26/10/2020 14:33
"Working group" studies the state of investment projects in the Shurtan oil and gas production department
26/10/2020 14:33
Tashkent, Uzbekistan (UzDaily.com) -- Members of the "Working Group" headed by the Chairman of the Board of Uzbekneftegaz Mehriddin Abdullayev got acquainted with the progress of construction and installation works carried out at the final stage of the investment project "Modernization of propane-butane separation equipment 1, 2 and 5 "in the main building of the Shurtan oil and gas production department.
According to the technical solutions developed within the framework of the project, modernization work is underway to increase the separation of the propane-butane mixture from the composition of natural gas in the existing units for extracting propane-butane mixtures.
As a result, an additional 61,000 tonnes of liquefied gas will be produced per year and directed to the needs of the country's population, utilities and industry.
In order to implement the project, along with the Ukrainian "Sumy NPO", the Russian "KMPO", "NIPI NG PETON", "Electrostandard-device", the Swiss "Endress + Hauser" and other foreign companies, the supply of technological equipment is carried out under contracts for the purchase of equipment manufactured by JSC "Uzbekkhimmash Plant" and "Uzpromarm".
To date, measures have been taken to increase the production of liquefied gas through the stage-by-stage implementation of project activities using equipment and apparatus supplied under the project. In particular, work was carried out to install separators in the 2nd and 5th branches of the propane-butane mixture production unit, install new Peton contact elements instead of the internal elements of the Deethanizer columns, replace obsolete control valves, install a methanol spraying system and other technological solutions.
To date, in accordance with the instructions of the Chairman of the Management Board of Uzbekneftegaz, technological solutions have been developed and implemented for the accelerated commissioning of devices based on the population's demand for liquefied gas in the autumn-winter period. Installation of the supplied technological devices and equipment, installation of main inter-shop pipelines is 98% complete.
According to the project, work is underway to commission a number of technological devices for setting up and connecting the main process pipes. In order to complete the construction and installation works and launch the project in a short time, the Chairman of the Management Board gave appropriate instructions and instructions, and the employees responsible for solving problematic issues related to production and construction and installation works were instructed.
Installation work by the general contractor Mubarakneftegazmontazh JSC continues at an accelerated pace.
The Chairman of the Board emphasized the need for the timely launch of the project and taking measures to provide the population and the economy with liquefied natural gas in the autumn-winter period. Responsible managers were again given the task of organizing work within the framework of the project, with strict adherence to quarantine measures, it must be remembered that quarantine restrictions were not canceled, but eased.