At the Bukhara refinery, intensive work is underway to prepare for the autumn-winter period
19/09/2020 14:38
At the Bukhara refinery, intensive work is underway to prepare for the autumn-winter period
19/09/2020 14:38
Tashkent, Uzbekistan (UzDaily.com) -- Specialists of the Bukhara refinery are conducting a comprehensive preparation of the facilities of the production, transport and energy infrastructure of the enterprise for operation in the autumn-winter period of 2020-2021.
The enterprise analyzes all possible production risks, identifies problem areas, on the basis of which plans for targeted measures are formed to eliminate them.
On the basis of the action plan, timely monitoring of the work is carried out. All divisions of the enterprise involved in production take part in the preparation.
The plan envisages overhaul and current repairs of pipelines, replacement of valves, renewal of thermal insulation of pipelines, preparation of power supply facilities, repair of the roof of industrial, warehouse and office buildings, preparation of vehicles of emergency dispatch services for work in winter conditions.
Much attention is paid to equipping facilities with technological security equipment.
To date, a lot of work has been done on revision and repair:
- shut-off valves on the steam and heating lines in the commodity - raw materials shop;
- valves on the cooling line of process pumps in the commodity - raw materials shop;
- on the line of the main water pipeline from the III-water lift to the Neftchi settlement of the BNPZ;
- heating systems for all administrative buildings of the plant;
- valves in the building of the educational building and the laundry of the plant;
Also, steam and liquid leaks through the gland packing of valves and valves on heating lines in all installations of the main production workshop were eliminated.
Work was carried out to replace: the pipeline on the hot water supply and return lines in the FOC building, valves and pipelines on the hot water supply and return lines in the warehouse, the central plant laboratory, the nitrogen-oxygen station, the administrative building (ABK), shut-off valves of the heating system of city sewage treatment plants and a defective section of the main fire-fighting water conduit В-2 Ø 325 mm in quarter 15, along the road No. 28.
All repair work is carried out in compliance with the requirements of technical and fire safety regulations.