Tashkent, Uzbekistan (UzDaily.com) -- Due to the completion of the heating season of 2018-2019 and with the aim of high-quality preparation for the next heating season of 2019-2020 in Tashkent city, the state unitary enterprise “TOSHISSIQQUVVATI” is starting to rebuild the worn-out section of the heating main on the Small Ring Road (formerly General Uzakov Street) in Shayhantahur district.
Work is planned to be carried out without shutting down the hot water supply from 27 March 2019 to 27 April 2019.
During this period, care and attention of drivers and pedestrians in the area of work is required.