Uzbekenergo to complete projects US$1.243bn in 2016
14/01/2016 11:48
Uzbekenergo to complete projects US$1.243bn in 2016
14/01/2016 11:48
Tashkent, Uzbekistan (UzDaily.com) -- Uzbekenergo (Uzbek Energy) is planning to complete implementation of the projects for US$1.243 billion soums.
Sputnik news agency reported that the Government of Uzbekistan approved a schedule of realization of five projects, which were included to investment project for 2016.
In particular, South Korea’s Daewoo and Hyundai completed construction of two combined cycle power plants (CCPP) with a total capacity of 900 MW at Talimarjan thermal power plants (TPP). The project cost is US$920.5 million.
Harbin Electric International Company Ltd (China) will complete construction of a new power unit of 150 MW with heating extraction for burning of high-ash coal Angren thermal power plant (TPP) in the Tashkent region. The cost of the project exceeds US$242 million.
Uzbekenergo also plans in 2016 to complete the construction of the power supply for the two railway stations in the east and south of the country with a total cost of US$74.5 million.